ScrumWorks Reports Guide - Version 1.8.0
This guide will help you understand the reporting related
features of the ScrumWorks Desktop Client. The
information contained within this guide is designed to
give you in-depth knowledge of how these features work
so that you may use them to their full potential.
Dashboard Report
The Dashboard Report shows the status of releases across products selected
for inclusion in the report. When a product is selected to appear in the Dashboard report,
the progress against the work allocated to the release is superimposed on a chronological
representation of releases (as indicated by the release begin and end dates).
Work progress is measured in "Product Backlog Effort units". For example, a progress bar
that shows "217/274 (79%)" means that of 274 Product Backlog effort units currently
scheduled for inclusion in the release, 217 have been marked "Done". This means that
79% of the currently scheduled work has been completed by the team.
The work progress is then superimposed on a chronological schedule. If the release is
currently active (i.e., today's date is between the begin and end dates associated with the release)
a red line will indicate "Today". Thus the work progress can be seen
in clear relation to the proposed schedule.
This report updates itself each time there is a change to the system. In Scrum, changes
are accepted as a normal occurance in project work. If the release dates, total backlog
effort points or number of points marked "Done" change, then the Dashboard report will
mirror the changes automatically.
» top

A release must have an associated beginning and ending date to show up in the Dashboard report.
Two date fields are supplied for creating a dashboard report: a start date and
an end date.
Releases occurring in this range are included in the report. The
release doesn't have to be entirely contained within the dates; any release that
overlaps the date range selected will be included in the report.
In ScrumWorks, begin and end dates associated with releases imply a schedule. The
Warning Level lets users customize how releases that are behind schedule appear.
When a release is behind schedule, the color of the progress bar
can be either yellow or red, and the Warning Level dictates whether red or yellow is displayed.
The Warning Level is the threshold above which ScrumWorks displays a red bar to indicate that the
release is behind schedule by a percentage greater than or equal to the Warning Level value.
For example, if the Warning Level is set to 10%, the progress bar for the release will be
yellow if the project is only 5% behind schedule but red if the project is 11% behind schedule.
» top
The Dashboard report is accessed as a PDF file; however, a preview is available before the final PDF
is published. To preview a report:
- In the left pane, select all Products for inclusion in the report.
- Then adjust the Date and Warning Level settings as desired.
- Click the Generate button to see a preview of the Dashboard report.
» top
Once satisfied with the preview, click the Launch button to generate the actual report in PDF format.
Take note of the URL associated to the report. The URL is accessible from outside of ScrumWorks and is a
convenient way to reference the report at a later time or to share the report via email. For convenience,
the Report URL is accessible directly without the need to log into ScrumWorks. As a result,
be sure to keep the Report URL private if privacy is a concern.
» top
Product Burndown
The product burndown chart shows how much work is left
to do in the product. It shows the amount of backlog
effort remaining at the beginning of each Sprint. There
is a basic product burndown chart and an enhanced
product burndown chart available in ScrumWorks.
This is a product burndown chart as defined by page
11 of
Agile Project Management with Scrum.
Here is an example of the basic product burndown
chart:

Each bar represents the amount of product backlog
remaining on the first day of the Sprint. For each
selected release, the product backlog consists of
all uncommitted backlog items for that release and
all committed backlog items in sprints in that
release.
Each backlog item maintains its own effort history,
recording entries as the backlog item is
re-estimated over time. This historical view of each
backlog item is used to calculate the total effort
remaining on the first day of each sprint.
Backlog items committed to sprints can be marked
"Done". This indicates to the product burndown that
this backlog item's effort is now considered as work
that is done; work that has been burned. This effort
is then excluded from the total effort remaining and
causes the sprint bar heights to decrease. Bar
heights can also go down if backlog items are
re-estimated at a lower effort value. The bars
increase in height when new backlog items are added
or existing backlog items are re-estimated at an
increase.
Data for sprints ending within one week of
each other are merged into one bar. This is
especially useful when multiple teams are working
from the same product backlog. It helps give a more
accurate (and less crowded) picture of the work being
done.
» top
Enhanced Product Burndown
This chart distinguishes between work completed and
work added/removed. This can help forecast product
completion. The Velocity Trendline shows the rate at
which work is completed. The Work Added/Removed
Trendline shows the trend of commitment change and
backlog re-estimation. A new baseline is drawn as a
result of work added or removed through the last
completed sprint. If work is completed faster than
it's added, ScrumWorks can estimate how many sprints
it will take to complete the product.
Here is an example of the enhanced product burndown
chart:

This chart shows that if the current trends
continue, project completion is forecast in 2-3
sprints.
The bar high positions on this chart are plotted by
subtracting the amount of backlog burned during the
prior Sprint. Each subsequent Sprint bar high
position will either go down or stay flat, but never
go up.
The lower portions extending below the previous
Sprint's low position denote new backlog items added
or additional effort as a result of re-estimation.
The low bar position can also go up from the
previous sprint. This happens when the total effort
decreases, either through the removal of product
backlog or a decrease caused by re-estimation of
existing backlog items.
For additional details about the enhanced product
burndown chart please refer to the ScrumWorks Wiki
link
EnhancedProductBurndownChart
Data for sprints ending within one week of
each other are merged into one bar. This is
especially useful when multiple teams are working
from the same product backlog. It helps give a more
accurate (and less crowded) picture of the work being
done.
» top
Use the release selection to specify which releases
are used for the product burndown. For each selected
release the burndown charts will sum the following:
-
Effort for all uncommitted backlog items in
the release
-
Effort for committed backlog items in sprints
within the release
Select the Build Chart button to re-display the
chart using the selected releases.
» top
An active sprint is where the current date falls
within that Sprint's begin and end dates. Any
currently active sprints are not included in any
trendline calculations. New baselines are drawn
using the last completed Sprint.
» top
Marking Backlog Items Done
To show that work has been completed use the backlog
editor to mark individual backlog items as "Done". The
product burndown chart uses this information to draw
the height of each of the sprint bars and to
calculate the velocity.
» top
Backlog Item Effort History and Creation Dates
The current product effort remaining on the first
day of each sprint is the value used to draw the
height of each of the sprint bars. Sometimes a
backlog item will be created after the start date of
the sprint for which this backlog item belongs. You
can adjust the creation date of this backlog item so
that it impacts the current sprint, backdating the
backlog item. Edit the first entry in the backlog
item's estimate history to the first day of the
Sprint you want it to impact. This allows for a more
precise graphical representation within the product
burndown.
Please see Edit Product Backlog
Item Estimate History for more details on
editing backlog item estimate history.
» top
References and Links to Further Reading
Sprint Change Report
This report summarizes changes to the outstanding backlog including work completed
this sprint, work added/removed from the product backlog, and how re-estimation affected
the product backlog.
» top
You can open the Sprint Change Report in one of two ways:
- Click "Reports" -> "Sprint Change Report"
- Open a Basic or Enhanced Product Burndown chart and select the "Sprint Change Report" tab
This presents you with a clickable chart. Single clicking a bar selects the sprint and gives you
a URL that contains your report. Double clicking the bar opens your report.
» top
The Sprint Change report is exported as an Excel spreadsheet file. Once
exported, the report can be manipulated as desired. The
report is divided into two sides. The left side of the report (with green headings) lists all
activity that lowered the product's Backlog Effort points. The right side (maroon heading)
indicates all activity that increased the product's Backlog Effort points.

» top